Convergent Battery Storage System – Ford Facility
S. & T. was selected as Convergent Energy +Power’s construction partner on a 4MW/8MWh battery energy storage system for a large Industrial Facility in Windsor, Ontario. The scope of work included all heavy civil, concrete, ground grid, u/g electrical infrastructure, installation of all battery system components as well as the 13.8kV connection to the local distribution system.